2022-23 Capital Projects
In February 2022, the provincial government announced an update to its school capital plan. Click here to read the news release.
Click here to view the Department of Education and Early Childhood Development’s multi-year capital plan.
Supporting Enrolment Growth
Enrolment in HRCE schools continues to grow. At some schools, this growth is causing capacity pressures. To support school communities, modular classroom additions will be constructed at three HRCE schools and six schools will receive portable classrooms during the summer of 2022.
Georges P. Vanier Junior High
- September 6, 2022 - Completion
- July 14, 2022 - Project Update
- May 2, 2022 - Announcement
Millwood High
- September 6, 2022 - Completion
- July 19, 2022 - Project Update
- May 2, 2022 - Announcement
Sackville Heights Elementary
- September 6, 2022 - Completion
- July 18, 2022 - Project Update
- May 2, 2022 - Announcement
Charles P. Allen High
- September 6, 2022 - Completion
- July 13, 2022 - Project Update
- May 12, 2022 - Announcement
Holland Road Elementary
- September 6, 2022 - Completion
- July 19, 2022 - Project Update
- May 12, 2022 - Announcement
Le-Marchant St. Thomas Elementary
- September 6, 2022 - Completion
- July 19, 2022 -Project Update
- May 12, 2022 - Announcement
Portland Estates Elementary
- September 6, 2022 - Completion
- July 19, 2022 - Project Update
- May 12, 2022 - Announcement
Sackville Heights Junior High
- September 6, 2022 - Completion
- July 19, 2022 - Project Update
- May 12, 2022 - Announcement
St. Margaret's Bay Elementary
- September 6, 2022 - Completion
- July 19, 2022 - Project Update
- May 12, 2022 - Announcement
Capital Repair Projects
Some of the larger capital repair projects undertaken during this fiscal year:
Bicentennial School
- August 30, 2023 - Completion
- June 16, 2023 - Project Update
- May 15, 2023 - Project Update
- April 17, 2023 - Project Update
- March 23, 2023 - Project Update
- February 24, 2023 - Project Update
- January 13, 2023 - Project Update
- November 10, 2022 - Project Update
- September 16, 2022 - Project Update
- June 16, 2022 - Announcement
Asbestos Testing
On Thursday, December 8, out of an abundance of caution, the Halifax Regional Centre for Education (HRCE) closed Bicentennial School after receiving test results indicating higher than acceptable levels of asbestos present in two of the three rooms under construction. The school remained closed on Monday, December 12 and Tuesday, December 13 while more testing was completed.
The school re-opened on Wednesday, December 14 after the HRCE received approval from the Nova Scotia Department of Labour, Skills, and Immigration along with clear test results from a third-party expert.
The following reports capture all relevant details:
- 30128 – Bicentennial School – MicroVAC Report, December 8, 2022
- 30128 – Report 02 – Bicentennial School – MicroVAC Report - REV, December 9, 2022
- 30171 – Bicentennial School – Background Air Monitoring – Report 02, December 11, 2022
- 30171 – Bicentennial School – MicroVAC Report, December 13, 2022
- 319996 – Occupancy and Dust Results Letter, 85 Victoria Rd, Dartmouth, NS, HRCE, 13Dec2022
Letters to Families
- December 13, 2022 - Test Results
- December 13, 2022 - School Reopening Announcement
- December 12, 2022 - School Closure Update
- December 11, 2022 - School Closure Update
- December 8, 2022 - School Closure Announcement
Additional Information
- 30105 - Report 3 - Bicentennial School - Perimeter Air Monitoring, November 23, 2022
- 30105 - Report 4 - Bicentennial School - Perimeter Air Monitoring, November 24, 2022
- 30105 - Report 6 - Bicentennial School - FC Report, November 24, 2022
- 30138 - Report 1 - Bicentennial School - Enclosure Pre-Inspection, December 1, 2022
- 30138 - Report 2 - Bicentennial School - Perimeter Air Monitoring, December 2, 2022
- 30138 - Report 3 - Bicentennial School - Post-Abatement Inspection, December 2, 2022
- 30138 - Report 4 - Bicentennial School - FC Report, December 2, 2022
Brookhouse Elementary
- March 1, 2023 - Completion
- November 10, 2022 - Announcement
Crichton Park Elementary
- April 3, 2023 - Completion
- October 21, 2022 - Announcement
Dutch Settlement Elementary
- March 1, 2023 - Completion
- October 21, 2022 - Announcement
Harold T. Barrett Junior High
- March 8, 2023 - Completion
- October 24, 2022 - Project Update
- September 1, 2022 - Announcement
Highland Park Junior High
- April 3, 2023 - Completion
- October 21, 2022 - Announcement
John W. MacLeod - Fleming Tower Elementary
- May 11, 2023 - Completion
- May 5, 2023 - Announcement
Joseph Howe Elementary
- September 6, 2022 - Announcement
Rockingham Elementary
- April 3, 2023 - Completion
- January 13, 2023 - Project Update
- October 21, 2022 - Announcement
Tantallon Senior Elementary
- July 18, 2023 - Completion
- October 21, 2022 - Announcement
William King Elementary
- November 25, 2022 - Announcement