3608 |
SMART METERING PKG 2 |
G J CAHILL |
$99,997.00 |
December 17, 2013 |
3607 |
PLUMBING FIXTURE RETROFIT - PKG 2 |
G J CAHILL |
$94,700.00 |
February 25, 2014 |
3606 |
BAS CONTROLS - PKG 5 |
CONTROLS & EQUIPMENT |
$269,625.00 |
December 17, 2013 |
3605 |
BAS CONTROLS - PKG 4 |
CONTROLS & EQUIPMENT |
$225,100.00 |
December 17, 2013 |
3605 |
BAS CONTROLS - PKG 4 |
ADVANCED ENERGY MANAGEMENT |
$95,470.00 |
December 17, 2013 |
3604 |
LIGHTING - PKG 4 |
AINSWORTH |
$319,976.00 |
December 13, 2013 |
3603 |
LIGHTING RETROFIT - PKG 3 |
ENERGY NETWORK SERVICES |
$433,263.76 |
December 4, 2013 |
3602 |
MOD BIT ROOF - Sackville High |
A-TECH ROOFING |
$129,800.00 |
November 1, 2013 |
3600 |
RENO/ELEVATOR - Rocky Lake Jr High |
BLUNDEN CONSTRUCTION |
$677,000.00 |
November 12, 2013 |
3599 |
SITE WORK - Alantic Memorial |
OCEAN CONTRACTORS |
$396,200.00 |
October 22, 2013 |
3596 |
SMART METERING - PKG 1 |
ROCKINGHAM ELECTRIC |
$138,229.00 |
December 5, 2013 |
3595 |
BUILDING ENVELOPE UPGRADES PKG 1 |
ALL ANGLES ENERGY SOLUTIONS |
$56,190.00 |
December 16, 2013 |
3594 |
PLUMBING FIXTURE RETROFIT PKG 1 |
ATLANTICA MECHANICAL |
$98,252.00 |
December 10, 2013 |
3593 |
MECHANICAL/CONTROLS - MVEC |
G J CAHILL |
$105,355.00 |
November 8, 2013 |
3592 |
BAS CONTROLS PKG 2 |
ADVANCED ENERGY MGMT |
$296,047.00 |
September 23, 2013 |
3591 |
LIGHTING RETROFIT - SIX SCHOOLS |
DYNAMIC ENERGY SERVICES LTD |
$417,098.00 |
November 8, 2013 |
3590 |
LIGHTING RETROFIT - Halifax West |
ENERGY NETWORK SERVICES INC |
$285,689.00 |
November 8, 2013 |
3589 |
BIOMASS HEATING - Millwood Elem |
ATLANTICA MECHANICAL |
$1,019,800.00 |
February 26, 2014 |
3588 |
NATURAL GAS CONVERSION - Citadel High |
GJ CAHILL & COMPANY |
$1,231,100.00 |
January 8, 2014 |
3587 |
NEW ENTRANCE - Gorsebrook |
BLUNDEN CONSTRUCTION |
$105,000.00 |
September 17, 2013 |